What Is a Bid Bond?
A bid bond is a type of contract surety bond submitted by a contractor along with their bid proposal on a construction project. The bid bond serves as a financial guarantee to the project owner (obligee) that the contractor (principal) will:
- Honor their bid price — The contractor will not withdraw their bid during the bid holding period or refuse to enter into the contract at the bid price if selected as the lowest responsive, responsible bidder.
- Execute the contract — The contractor will sign the formal construction contract within the time specified in the bid documents.
- Provide the required performance and payment bonds — Upon contract award, the contractor will furnish the performance bond and payment bond required by the contract, securing the project owner's investment in the work.
Bid bonds are a critical pre-qualification tool in the construction bidding process. By requiring a bid bond, the project owner ensures that every bidder has been pre-approved by a surety company, which means the surety has already evaluated the contractor's financial strength, construction experience, and ability to perform the work. This dramatically reduces the risk of awarding a contract to a contractor who cannot actually perform.
If the winning contractor fails to honor any of these obligations, the surety company that issued the bid bond is liable to the project owner for damages, up to the penal sum (face value) of the bid bond.
How Do Bid Bonds Work?
Like all surety bonds, a bid bond involves a three-party relationship:
- Principal (Contractor) — The contractor who submits the bid and purchases the bid bond. The principal is the party making the guarantee through the surety.
- Obligee (Project Owner) — The entity that requires the bid bond and is protected by it. On public projects, this is typically a government agency (federal, state, county, or municipal). On private projects, this is the property owner or developer.
- Surety (Bonding Company) — The insurance company or surety company that issues the bid bond and guarantees the contractor's bid obligations. The surety has underwritten the contractor and determined they are capable of performing the work if awarded the contract.
The bid bond process typically works as follows:
- A project owner issues an Invitation for Bids (IFB) or Request for Proposals (RFP) that specifies bidders must submit a bid bond in a certain amount (e.g., 5%, 10%, or 20% of the bid).
- The contractor contacts their surety bond agent to request a bid bond for the specific project. The surety reviews the project details, bid amount, and the contractor's qualifications.
- If approved, the surety issues the bid bond, which the contractor submits along with their sealed bid.
- After bids are opened, if the contractor is the apparent low bidder and is awarded the contract, they must sign the contract and provide performance and payment bonds within the specified timeframe.
- Once the contract is executed and the performance and payment bonds are in place, the bid bond is exonerated (released) and is no longer in effect.
- If the contractor fails to execute the contract or provide the required bonds, the project owner makes a claim on the bid bond.
Who Needs a Bid Bond?
Bid bonds are required in a wide range of construction bidding scenarios:
- Federal construction projects — The Miller Act (40 U.S.C. §§ 3131–3134) requires bid bonds on most federal construction projects. The Federal Acquisition Regulation (FAR) typically requires a bid guarantee of 20% of the bid price, not to exceed $3 million.
- State and municipal projects — Every state has a Little Miller Act that imposes bonding requirements on state-funded public construction projects. Most require bid bonds in the range of 5% to 10% of the bid amount.
- Private construction projects — Many private project owners, developers, and lenders require bid bonds on larger projects to ensure the integrity of the competitive bidding process.
- General contractors — GCs bidding on bonded projects must submit bid bonds as part of their bid packages.
- Subcontractors — On some projects, the general contractor or project owner requires subcontractors to furnish bid bonds for their portion of the work.
- Specialty trade contractors — Electrical, mechanical, plumbing, HVAC, and other specialty contractors may need bid bonds when bidding on public or bonded private projects.
In essence, any contractor or subcontractor bidding on a project where the bid documents require a bid bond will need to obtain one from a surety company before submitting their bid.
Bid Bond Amounts: How Much Coverage Is Required?
The bid bond amount (also called the penal sum) is set by the project owner and stated in the bid documents. The amount represents the maximum the surety will pay if the contractor defaults on their bid obligations. Common bid bond amounts include:
- 5% of the bid amount — Common on many state and municipal projects and smaller private projects.
- 10% of the bid amount — Frequently required on state highway projects and larger municipal contracts.
- 20% of the bid price (federal projects) — Under the Federal Acquisition Regulation (FAR 28.101-2), bid guarantees on federal construction contracts are typically set at 20% of the bid price, with a maximum penal sum of $3 million.
For example, if a contractor submits a bid of $1,000,000 on a project requiring a 10% bid bond, the bid bond would have a penal sum of $100,000. If the same contractor bids on a federal project requiring a 20% bid bond, the penal sum would be $200,000.
It is important to note that the bid bond amount caps the surety's liability but does not necessarily represent the actual damages. The actual claim amount is calculated as the difference between the defaulting contractor's bid and the next lowest responsive bid, up to the penal sum of the bond.
How Much Do Bid Bonds Cost?
One of the most common questions contractors ask is about the cost of a bid bond. At Surety Specialist, bid bonds are always free — no premiums, no fees, no hidden costs, regardless of whether you have an existing bonding line or not.
While many agencies charge $100 to $350 for standalone bid bonds, we believe contractors should never have to pay for the opportunity to compete on a project. We provide bid bonds at absolutely no charge as part of our commitment to helping contractors win more work.
Why are our bid bonds free?
- No upfront cost, ever — Whether you're a first-time applicant or a long-standing client, you will never pay a fee for a bid bond through Surety Specialist.
- We invest in your success — A bid bond is the first step in the bonding process. When you win the project, we earn our premium on the performance and payment bonds that follow. Your success is our success.
- SBA Surety Bond Guarantee Program — Contractors who qualify through the U.S. Small Business Administration's Surety Bond Guarantee Program can also benefit from the SBA's guarantee of up to 90% of the surety's loss, making it even easier for newer or smaller contractors to get bonded.
Because the surety's real financial exposure comes from the performance and payment bonds (not the bid bond itself), we view the bid bond as an investment in our relationship with you — not a revenue opportunity.
How to Qualify for a Bid Bond
When a contractor applies for a bid bond, the surety is not just evaluating the contractor's ability to submit a bid — it is evaluating whether the contractor can perform the entire project and provide the required performance and payment bonds. The surety's underwriting process examines several key factors, often referred to as the "Three Cs" of surety underwriting:
1. Character
- Personal credit score — Sureties review the personal credit of the business owner(s) and any individual indemnitors. A credit score of 680 or higher is generally preferred, though scores of 700+ receive the best rates and highest capacity. Some sureties will work with scores in the low 600s with compensating factors.
- Industry reputation — References from project owners, architects, subcontractors, and suppliers who can attest to the contractor's reliability and professionalism.
- Legal history — Any history of lawsuits, liens, judgments, bankruptcies, or criminal matters may affect qualification.
2. Capacity
- Construction experience — The surety looks for a proven track record of successfully completing projects similar in size, scope, and type to the project being bid. A contractor who has completed ten $500,000 highway projects will be viewed favorably for a $750,000 highway bid, but may face scrutiny bidding on a $5 million building project in an unfamiliar sector.
- Key personnel — The experience and qualifications of project managers, superintendents, and estimators on the contractor's team.
- Equipment and resources — Adequate owned or leased equipment, established relationships with subcontractors, and sufficient staffing capacity.
- Current work backlog — The surety evaluates the contractor's work-in-progress schedule to ensure they are not overextended. Taking on more work than the contractor can manage is a leading cause of contractor failure.
3. Capital
- Financial statements — Business financial statements (balance sheet, income statement, cash flow statement) are the cornerstone of surety underwriting. For larger bonds, CPA-prepared, reviewed, or audited financial statements are required. For bonds under $500,000, many sureties accept in-house or compiled statements.
- Working capital — Current assets minus current liabilities. Sureties want to see positive working capital sufficient to fund the project's cash flow needs. A general rule of thumb is that working capital should be at least 10% to 15% of the single largest project and the total bonded backlog.
- Net worth — Total assets minus total liabilities. A strong net worth demonstrates the contractor's long-term financial stability.
- Bank line of credit — Access to bank financing provides an additional cash flow safety net.
- Personal financial statement — The surety typically requires personal financial statements from the business owner(s), as they will be signing a personal indemnity agreement.
What Documentation Will You Need? A General Guide by Bond Size
Because a bid bond is the gateway to the performance and payment bonds that follow, the surety's underwriting for a bid bond is really about determining whether it can issue those follow-on bonds. The level of documentation required depends largely on the size of the bond. Here are the general tiers — keep in mind that bonding is highly individualized, and an experienced surety agent can often find solutions outside these parameters:
| Bond Size | Typical Requirements | What to Expect |
|---|---|---|
| Under $1 million | Credit-only program | With good personal credit (typically 680+), many sureties can approve bonds based on your credit profile alone — no business financial statements required. This is the fastest path to getting bonded. |
| $1M to $3 million | Internal financials or CPA compilation | In-house (internally prepared) financial statements or a CPA compilation showing adequate working capital and net worth. Full CPA-reviewed statements are not typically required at this level, though they can strengthen your application. |
| Over $3 million | CPA-reviewed financials | CPA-reviewed financial statements prepared on a percentage-of-completion basis, along with open and closed job schedules (work-in-progress reports). This gives the surety a clear picture of your current project commitments and profitability. |
| Credit challenges (up to $500K) | SBA Bond Guarantee Program | If your credit isn't strong enough for a standard program, the SBA Surety Bond Guarantee Program can help you get bonded on projects up to $500,000 through the streamlined QuickApp process — and larger with full SBA review. |
These are general rules of thumb, not hard lines. Every contractor's situation is different, and surety underwriting is highly subjective. Factors like industry experience, project type, and your relationship with your surety agent all play a role. At Surety Specialist, we work with 80+ sureties specifically to find the right fit for your situation — contact us to discuss your bonding needs.
What Happens When a Bid Bond Is Called?
A bid bond claim (also called "calling" the bid bond) occurs when a contractor fails to fulfill the obligations guaranteed by the bid bond. The most common triggers for a bid bond claim are:
- The contractor withdraws their bid after bid opening but before the bid holding period expires.
- The contractor refuses to sign the contract after being selected as the winning bidder.
- The contractor fails to provide the required performance and payment bonds within the time specified in the bid documents.
When a bid bond is called, the project owner's damages are calculated as the difference between the defaulting contractor's bid and the next lowest responsive, responsible bid, up to the penal sum of the bid bond. Here is how it works in practice:
Example of a Bid Bond Claim
Consider a project where three contractors submit bids:
- Contractor A (lowest bidder): $800,000
- Contractor B (second lowest): $860,000
- Contractor C (third lowest): $920,000
The project requires a 10% bid bond, so Contractor A's bid bond has a penal sum of $80,000. If Contractor A withdraws their bid or fails to execute the contract, the project owner awards the project to Contractor B at $860,000. The damages are:
$860,000 − $800,000 = $60,000
Since $60,000 is less than the $80,000 penal sum, the surety pays the project owner $60,000. Contractor A is then obligated to reimburse the surety the full $60,000 under the General Indemnity Agreement (GIA) that was signed when the bond was issued.
If the difference had been $95,000 (for example, if the next bid were $895,000), the surety's liability would be capped at the $80,000 penal sum, and the project owner would absorb the remaining $15,000 in additional cost.
The Bid Bond Claim Process
The claim process for a bid bond typically follows these steps:
- Default notification — The project owner notifies the contractor that they have been awarded the contract and must execute it within the specified timeframe (typically 10 to 30 days after notice of award).
- Contractor default — If the contractor fails to execute the contract or provide the required bonds, the project owner formally declares the contractor in default of their bid obligations.
- Claim submission — The project owner submits a written claim to the surety company that issued the bid bond, providing documentation including the bid tabulation, notice of award, evidence of the contractor's failure to execute, and the re-award or re-bid documentation.
- Surety investigation — The surety reviews the claim to verify its validity. This includes confirming the bid was responsive, the contractor was properly notified, and the claim amount is correctly calculated.
- Payment or resolution — If the claim is valid, the surety pays the project owner the calculated damages (the spread between the defaulting bid and the next bid), up to the bid bond's penal sum. The surety may also attempt to negotiate a settlement if the circumstances warrant.
- Indemnification — After paying the claim, the surety exercises its right of indemnification against the contractor (principal) and any personal indemnitors, seeking full reimbursement of the claim payment plus any costs incurred in investigating and resolving the claim.
Benefits of Bid Bonds
Benefits for Project Owners
- Pre-qualification of bidders — A bid bond certifies that the contractor has been vetted by a surety and has the financial strength, experience, and capability to perform the work. This eliminates unqualified bidders before the award stage.
- Financial protection — If the winning bidder defaults, the project owner is compensated for the additional cost of awarding the contract to the next lowest bidder, up to the bond's penal sum.
- Bid integrity — Bid bonds discourage "bid shopping" (contractors submitting low bids they cannot honor in hopes of negotiating higher prices later) and other manipulative bidding practices.
- Project continuity — By ensuring that bidders are bondable, bid bonds reduce the risk of delays caused by a winning bidder who cannot obtain performance and payment bonds after award.
- No cost to anyone — The project owner pays nothing for the bid bond, and through Surety Specialist, the contractor pays nothing either — bid bonds are always free.
Benefits for Contractors
- Demonstrates credibility — A bid bond signals to project owners that the contractor is financially sound and professionally qualified. It serves as a third-party endorsement from the surety company.
- Access to larger projects — Many public and private projects are only open to bonded contractors. Having a bid bond (and the underlying bonding line) opens doors to projects that unbonded competitors cannot access.
- Competitive advantage — Bonded contractors are viewed more favorably by project owners, architects, and construction managers, often gaining a competitive edge in the bidding process.
- Always free — Bid bonds through Surety Specialist are always free, regardless of your bonding history — making them an unbeatable value for the credibility they provide.
- Preserves cash — Unlike bid deposits or cashier's checks (which tie up the contractor's capital), a bid bond allows the contractor to preserve their cash and working capital for project operations.
Bid Bond vs. Bid Deposit: What Is the Difference?
Some project owners accept a bid deposit (also called bid security) as an alternative to a bid bond. Both serve the same purpose — guaranteeing that the winning bidder will enter into the contract — but they differ in key ways:
| Feature | Bid Bond | Bid Deposit |
|---|---|---|
| Form | Surety bond issued by a bonding company | Cash, cashier's check, certified check, or letter of credit |
| Cost to Contractor | Always free through Surety Specialist — no fees, no premiums | Ties up the full deposit amount in cash or bank instruments |
| Pre-Qualification | Yes — surety has vetted the contractor's financial strength and capability | No — having cash does not demonstrate construction ability |
| Impact on Working Capital | None — contractor's cash remains available for operations | Significant — cash is held until bids are released or contract is executed |
| Return of Funds | Bond is exonerated upon contract execution; no funds to return | Deposit returned to unsuccessful bidders after award; returned to winner after contract execution |
| Claim Amount | Difference between defaulting bid and next lowest bid, up to penal sum | Full deposit amount is typically forfeited upon default |
For most contractors, a bid bond is the preferred option because it preserves cash flow and provides the added benefit of surety pre-qualification. Project owners also benefit because a bid bond provides greater assurance that the contractor can actually perform the work.
Frequently Asked Questions About Bid Bonds
A bid bond is a type of contract surety bond that guarantees a contractor will honor their bid price and enter into the contract if awarded the project. It also guarantees the contractor will provide the required performance and payment bonds upon contract execution. Bid bonds protect project owners from frivolous or unreliable bids by ensuring contractors are financially and professionally capable of completing the work they bid on. The bid bond involves three parties: the principal (contractor), the obligee (project owner), and the surety (bonding company).
At Surety Specialist, bid bonds are always free — no premiums, no fees, no hidden costs. Whether you have an established bonding line or you're applying for the first time, you will never pay for a bid bond through our agency. While many competitors charge $100 to $350 for standalone bid bonds, we provide them at no charge because we believe contractors shouldn't have to pay for the opportunity to compete.
Bid bond amounts are set by the project owner and stated in the bid documents. They typically range from 5% to 10% of the contractor's bid amount on state and municipal projects. On federal projects, the Federal Acquisition Regulation (FAR) requires a bid guarantee of 20% of the bid price, with a maximum penal sum of $3 million. The bid bond amount represents the maximum the surety will pay if the contractor defaults on their bid obligations.
If a contractor withdraws their bid or fails to execute the contract after being awarded the project, the project owner can make a claim against the bid bond. The damages are calculated as the difference between the defaulting contractor's bid and the next lowest responsive bid, up to the penal sum of the bid bond. For example, if the contractor bid $500,000 and the next lowest bid is $550,000, the surety would pay the project owner $50,000. The contractor is then required to reimburse the surety under the indemnity agreement.
A bid bond is valid for the bid holding period specified in the bid documents — typically 60 to 120 days after bid opening. During this period, the contractor cannot withdraw their bid without triggering a potential claim on the bid bond. Once the contract is executed and the required performance and payment bonds are in place, the bid bond is exonerated (released) and is no longer in effect. If the contractor is not awarded the contract, the bid bond is automatically exonerated after the award is made to another bidder or the bid holding period expires.
Yes, it is possible to obtain a bid bond with less-than-perfect credit. For bond needs under $1 million, many sureties offer credit-only programs that can work with a range of credit profiles. For contractors with significant credit challenges, the SBA Surety Bond Guarantee Program provides a pathway for bonds up to $500,000 through the streamlined QuickApp process — and larger projects through full SBA review. The SBA guarantees up to 90% of the surety's loss, which encourages sureties to approve contractors who might not qualify under standard criteria. Additionally, some specialty sureties place greater weight on construction experience and financial strength rather than credit score alone. With access to 80+ surety partners, we can often find solutions for contractors with credit challenges.
A bid bond is a surety bond issued by a bonding company that guarantees the contractor will honor their bid, while a bid deposit is a cash deposit, cashier's check, or certified check submitted as financial security. The key advantage of a bid bond is that it does not tie up the contractor's cash — the surety provides the guarantee. A bid bond also provides the project owner with assurance that the contractor has been pre-qualified by the surety, confirming their financial strength and capability. With a bid deposit, the contractor must surrender actual funds that are held until the bid period expires or the contract is awarded.
If you have an established bonding line with a surety, bid bonds can often be issued the same day or within 24 hours. For new applicants, the initial bonding approval process may take 1 to 5 business days for smaller projects (under $500,000) with streamlined underwriting, or 1 to 2 weeks for larger projects requiring full financial review. We recommend contractors establish a bonding line well in advance of any bid deadline to avoid last-minute delays. Contact us as early as possible to begin the process.
Bid bonds are not legally required on private projects, but many private owners and developers choose to require them. On public projects, bid bonds are almost always required — federal projects over $150,000 mandate them under the Miller Act, and most state and local governments require them under their own Little Miller Acts.
Private owners who require bid bonds benefit from the surety's prequalification process: a surety will not issue a bid bond unless it has evaluated the contractor's financial strength, experience, and capability — providing the owner with assurance that all bidders are qualified to perform the work.
Once the contract is awarded and the winning contractor signs the contract and provides the required performance bond and payment bond, the bid bond's obligations are fulfilled and it is released. For losing bidders, their bid bonds are returned or released as soon as the contract is awarded to another contractor.
If the winning bidder fails to sign the contract or fails to provide the required performance and payment bonds, the project owner can make a claim on the bid bond. The surety's liability is typically the difference between the defaulting bidder's price and the next lowest bid, up to the penal sum of the bid bond (usually 5% to 20% of the bid amount).
Getting pre-qualified (establishing a bonding line) before you need a bid bond offers significant advantages:
- Speed: With a bonding line in place, bid bonds can be issued same-day, so you never miss a bid deadline
- Know your capacity: You'll know your single and aggregate limits, so you can target projects you can actually bond
- Competitive advantage: Some bid solicitations require a surety letter of intent or bonding capacity letter — having one ready sets you apart from competitors
- Financial guidance: The prequalification process helps identify areas to strengthen in your financials before you need a bond urgently
We recommend every contractor establish a bonding line as early as possible — there is no cost to get pre-qualified. Contact us to start the process.
Request a Bid Bond Quote
Fill out the form below and one of our surety bond specialists will contact you within one business day with a personalized bid bond quote. There is no cost or obligation.