How we verified this page: Each row was read in the statute or regulation linked in the Source column on November 21 and 22, 2026. Georgia was read from a copy of the code dated March 28, 2024, because the official text is not freely accessible. Rows marked Confirm locally depend on a local rule or an older copy of the code and need a direct check. This page is general information, not legal advice. The solicitation or the approving agency's written requirements control on any specific project.

What a Bid Bond Requirement Looks Like

A bid bond guarantees that the bidder will honor its price and sign the contract, with the required performance and payment bonds, if it wins. Public owners set three things: the contract size at which bid security is required, the amount (usually a percentage of the bid), and the forms they accept in place of a bond.

Federal work follows one rule everywhere. State and local work does not: some states write the requirement into statute, some leave it to the awarding agency, and cities and counties often have their own rules. The table covers the federal rule and seven states. For any other state, the bid documents state the requirement.

Bid Security Requirements at a Glance

Jurisdiction When bid security is required Amount Source Notes
Federal Whenever a performance bond is required: construction contracts exceeding $150,000 At least 20% of the bid price, not to exceed $3 million FAR 28.101-1; 28.101-2; 28.102-1 A contracting officer may not require a bid guarantee unless a performance bond is also required. Construction contracts need a separate bid guarantee. Verified
Florida FDOT: construction contracts in excess of $150,000 Set by FDOT, not to exceed 10% of the preliminary estimate Fla. Stat. § 337.17 Cashier's check, bank money order, bank draft, certified check or surety bond. The surety must be a company recognized to execute bid bonds for federal contracts. Other Florida public owners set bid security in the bid documents. Confirm locally
Texas Counties: may be required on public works, or on a contract exceeding $100,000 5% of the total contract price Tex. Loc. Gov't Code § 262.032 Discretionary: the bid specifications "may require" it. The surety must be authorized to do business in Texas. Cities, state agencies and TxDOT set bid security under their own rules. Confirm locally
Georgia State and local public works with estimated bids over $100,000 Not less than 5% of the total amount payable under the contract O.C.G.A. § 13-10-20 (state); § 36-91-50 (local) A bid may not be withdrawn until 60 days after bid opening. Owners may require a bid bond on smaller projects. A 2025 law raised the floor of the local public works chapter to $250,000, so smaller local projects may fall outside § 36-91-50. Confirm locally
South Carolina State design-bid-build construction contracts, competitive sealed bidding, in excess of $100,000 At least 5% of the amount of the bid S.C. Code § 11-35-3030(1) A bidder with the wrong amount or bond rating gets one working day from bid opening to cure. Counties and cities set bid security in their own procurement ordinances. Verified
North Carolina State and local construction or repair work of $500,000 or more Not less than 5% of the proposal N.C.G.S. § 143-129 Cash, cashier's check, certified check, or a bid bond from a corporate surety licensed in North Carolina. The deposit is retained if the bidder does not sign within 10 days after award. Verified
Maryland State construction procurements expected to exceed the small procurement amount ($100,000; $200,000 for DGS and MDOT construction) At least 5% of the bid or price proposal Md. State Fin. & Proc. § 13-207 Surety bond, cash, or another form allowed by regulation. A bid without proper security must be rejected, with narrow exceptions. Counties and municipalities set their own rules. Verified
Washington, D.C. Construction contracts estimated to exceed $100,000 At least 5% of the amount of the bid D.C. Code § 2-357.01 Bond from a surety authorized in the District, cash, or another form satisfactory to the District. Bids are irrevocable after opening for the period stated in the invitation. Verified

Legend: Verified read in the current official text. Confirm locally set by a local rule, or read from an older copy of the code.

The Federal Rule

On federal construction, bid security follows the performance bond. Under FAR 28.101-1, a bid guarantee is required whenever a performance bond or a performance and payment bond is required, and a contracting officer may not ask for one otherwise. Performance and payment bonds are required on construction contracts exceeding $150,000 (FAR 28.102-1), so that is where federal bid guarantees begin.

The amount is at least 20% of the bid price, capped at $3 million (FAR 28.101-2). That is higher than the 5% most states use, which is why a contractor moving from state work to federal work sees a larger bid bond penal sum on the same size of job. See the Miller Act guide for the performance and payment bond side.

How the Seven States Differ

  • Where the line sits. North Carolina starts at $500,000. Georgia, South Carolina and Washington, D.C. start above $100,000. Maryland ties its threshold to the State's small procurement amount. Florida's statute speaks only to FDOT work.
  • Mandatory or optional. Texas counties may require a 5% bid bond; the statute does not make them. Georgia requires one above $100,000 and lets the owner require one below it.
  • What substitutes for a bond. Most of these statutes accept cash or a cashier's or certified check in place of a surety bond. A bond does not tie up cash, which is why contractors with a bonding line use one.
  • What happens after bid opening. Georgia holds bids open for 60 days. North Carolina keeps the deposit if the low bidder does not sign within 10 days after award.

Local owners are the gap in every statewide summary. A county, city, school district or authority can set a different percentage or accept different forms, so read the instructions to bidders on each job.

What a Bid Bond Costs

Bid bonds are free through Surety Specialist once your bonding line is established. The surety is paid when you win and the performance and payment bonds are issued. Use the bond cost calculator to estimate that premium before you price a bid.

Bid Bond Requirement Questions

At least 20% of the bid price, not to exceed $3 million (FAR 28.101-2). A bid guarantee is required whenever a performance bond is required, which on federal construction means contracts exceeding $150,000.

Five percent is the most common figure in the states covered here. Georgia, South Carolina, North Carolina, Maryland and Washington, D.C. each set a minimum of 5% of the bid or contract amount, and Texas counties may require 5% of the total contract price. Florida caps FDOT bid guaranties at 10% of the preliminary estimate. Local owners can set their own figure, so the bid documents control.

No. Each jurisdiction sets a contract size at which bid security starts: $500,000 or more in North Carolina, above $100,000 in Georgia, South Carolina and Washington, D.C., and above the small procurement amount in Maryland. Georgia and Washington, D.C. expressly let the owner require one on smaller contracts. In Texas, counties may require a bid bond but the statute does not make them.

Usually. The statutes covered here generally accept cash or a cashier's or certified check in the same amount, and North Carolina and Florida list those forms by name. A bid bond is the common choice because it does not tie up cash while the owner evaluates bids.

The bid security is at risk. North Carolina's statute, for example, keeps the deposit if the successful bidder does not execute the contract within 10 days after award or fails to give the required surety. Georgia generally does not allow a bid to be withdrawn until 60 days after bid opening.

Need a Bid Bond for an Upcoming Letting?

Tell us the owner, the bid date and the estimated contract amount. Once your bonding line is in place, bid bonds are issued at no charge.

Request a quote or call 877-914-0909

Ready to Bid?

Contact our team today for a free, no-obligation quote. We work with 80+ top-rated sureties and specialize in new contractors and tough accounts.

Request a Quote Call 877-914-0909