State Law Sets the Frame, the City or County Sets the Number
A subdivision bond guarantees that a developer will finish the public improvements tied to an approved plat: streets, drainage, water and sewer lines, sidewalks. The party that requires it is the city or county approving the development.
State law does one of three things. It caps what a local government can ask for (North Carolina, Texas counties). It sets a floor (South Carolina). Or it authorizes local governments to take security and leaves the amount to them (Florida, Maryland). The table shows which is which, and the local examples below show how different the practice can be inside one state.
Subdivision Guarantee Rules at a Glance
| Jurisdiction | What state law says | Amount | Source | Forms and notes |
|---|---|---|---|---|
| North Carolina | A subdivision regulation may provide for performance guarantees to assure completion of required improvements | Cap: may not exceed 125% of the reasonably estimated cost of completion | N.C.G.S. § 160D-804.1 | The developer chooses the type of guarantee. Initial duration is one year unless the developer needs longer. Release is due within 30 days of acknowledged completion. No guarantee may be required for maintenance after completion. Verified |
| South Carolina | Where improvements must be installed before plat approval, the developer may be permitted to post security instead | Floor: at least 125% of the cost of the improvement | S.C. Code § 6-29-1180 | Surety bond, certified check, or other instrument readily convertible to cash, in favor of the local government. Release, duration and maintenance terms come from local regulations. Verified |
| Texas | A county may require a bond for the roads, streets and drainage in a subdivision | Cap (counties): not to exceed the estimated cost of construction | Tex. Loc. Gov't Code §§ 232.004, 232.0045 | In lieu of the bond an owner may deposit cash, a letter of credit from a federally insured institution, or another acceptable guarantee. Cities set their own requirements. Confirm locally |
| Florida | If a local government requires infrastructure financial assurance for plat approval, it must accept commonly used forms | No statewide percentage; set by the county or city | Fla. Stat. § 177.071 | The statute names performance bonds, letters of credit and escrow agreements. A deficient assurance must be flagged in writing within 10 business days. Local practice varies; see Miami-Dade below. Confirm locally |
| Maryland | A planning commission may accept security instead of completed improvements before final plat approval | No statewide percentage; set by the local jurisdiction | Md. Land Use § 5-204(c) | May include a bond with surety, an irrevocable letter of credit, or any other form the local jurisdiction approves. Charter counties generally act under their own codes. Confirm locally |
| Georgia | Set in county and city development regulations | Set locally | County or city development code | We did not find a statewide statute fixing the amount or form. Requirements, including maintenance periods, come from the local code. Confirm locally |
| Washington, D.C. | No county-style subdivision bond; work in public space is permitted through the District Department of Transportation | Set by the permit | DDOT public space permit requirements | Security for work in public space is handled through the permit. Confirm the requirement with DDOT for the specific project. Confirm locally |
Legend: Verified read in the current official text. Confirm locally the amount or form is set by a local rule.
A Cap in One State, a Floor in the Next
North Carolina and South Carolina both use the figure 125%, and they mean opposite things. In North Carolina a local government may not require more than 125% of the estimated cost of completion, and the developer picks the form of guarantee. In South Carolina the security must be at least 125% of the cost of the improvement, so a local government can ask for more.
Texas goes the other way for counties: the bond may not exceed the estimated cost of the roads, streets and drainage, which is a 100% ceiling. Developers who work across state lines should budget the guarantee jurisdiction by jurisdiction.
Local Examples
These four were read on the official local page. They show why the approving agency's own requirements are the document to rely on.
- Miami-Dade County, Florida. The bond amount comes from a construction cost estimate calculated by a county engineer. The county's Platting and Traffic Review office states that it does not accept surety bonds as collateral for subdivision improvement bonds; it takes a cashier's check or a letter of credit. Source: Miami-Dade subdivision improvement bonds.
- City of Austin, Texas. Fiscal surety must equal the estimated cost for the City to do the work. Bond, escrow and letter of credit are all accepted for subdivisions, and bonds must come from companies on the U.S. Treasury's list of certified sureties. Source: Austin fiscal surety.
- City of Raleigh, North Carolina. Construction surety is 125% of the estimated construction cost of the improvements that remain incomplete, and 100% where the improvements are on a State-maintained road. Source: Raleigh UDO Sec. 8.1.3.
- Durham, North Carolina. The performance guarantee is 125% of the reasonably estimated cost to complete, and may be a surety bond, a letter of credit, or another form that gives equivalent security. Source: Durham UDO Sec. 12.11.
The Miami-Dade example matters for planning. Where a jurisdiction will not take a surety bond, the developer needs cash or a bank letter of credit, which draws on borrowing capacity. Our comparison of a letter of credit and a subdivision bond explains the difference.
What to Ask the Approving Agency
- What percentage of the engineer's estimate is the guarantee, and who prepares or approves the estimate?
- Which forms are accepted: surety bond, letter of credit, cash or escrow?
- Is there a required bond form, and does the surety need a particular rating or listing?
- How and when can the guarantee be reduced as work is completed?
- Is a separate maintenance or warranty guarantee required after acceptance, for how long, and in what amount?
What a Subdivision Bond Costs
Subdivision bonds typically cost 1% to 3% of the bond amount per year, and the premium continues until the improvements are accepted and the bond is released. First-time or higher-risk developers may see 3% to 5% and may be asked for collateral. Run the numbers in the bond cost calculator, and see subdivision bond underwriting for what a surety reviews.
Subdivision Bond Requirement Questions
The amount is set by the city or county, normally as a percentage of the estimated cost of the required improvements. State law shapes that figure in some states: North Carolina caps the guarantee at 125% of the estimated cost of completion, South Carolina requires at least 125% of the cost of the improvement, and Texas counties may not require more than the estimated cost of construction. Florida and Maryland leave the amount to the local jurisdiction.
It depends on the state. In North Carolina the developer chooses the type of guarantee. In Florida a local government that requires financial assurance for plat approval must accept commonly used forms, and the statute names performance bonds, letters of credit and escrow agreements. Local practice still varies: Miami-Dade County's platting office states that it does not accept surety bonds for subdivision improvement bonds.
Often, but the terms are local. North Carolina's statute requires release within 30 days after the local government acknowledges completion or receives a sealed engineer's certification. In most other places the reduction schedule is in the local development code or the developer agreement.
Many jurisdictions require one, with the period and amount set locally. North Carolina is an exception at the state level: its statute says no performance guarantee may be required for maintenance once an improvement is completed to the local government's specification.
Subdivision bonds typically cost 1% to 3% of the bond amount per year, charged for each year until the bond is released. First-time or higher-risk developers may see 3% to 5% and may be asked for collateral.