Important — Please Verify Before Relying: The statutes, thresholds, deadlines, and requirements on this page are provided for general educational purposes only and reflect our reading of the Maryland Code and COMAR as of November 2026. Laws change, and the specifics of your project may alter how they apply. Before making bonding or bidding decisions, verify current requirements directly with the contracting public body, the relevant Maryland agency, or an attorney licensed in Maryland. Nothing on this page constitutes legal advice.
Statutes and regulations cited on this page Compare every state: performance bond requirements by state and payment bond requirements by state. Also see bid bond requirements and subdivision bond requirements for this state.

Maryland Bonding Requirements Overview

Public construction bonding in Maryland is governed by the state's Little Miller Act, found in Title 17, Subtitle 1 of the State Finance and Procurement Article (§§ 17-101 through 17-111). Under § 17-103, before a public body awards a construction contract that exceeds the small procurement amount, the contractor must provide both payment security and performance security.

The Act reaches well beyond State agencies. Section 17-101 defines a "public body" as the State, a county, a municipal corporation or other political subdivision, a public instrumentality, or any governmental unit authorized to award a contract.

Maryland differs from most states in two ways. The statute does not set the bonds at 100% of the contract: it requires payment security of at least 50% of the total amount payable and leaves performance security at an amount the public body considers adequate. And the threshold is not a fixed dollar figure written into the bond statute. Both points are covered below.

The threshold: tied to the small procurement amount

Section 17-103 applies to a construction contract "exceeding the small procurement amount specified in § 13-109." Section 13-109 defines a small procurement as one where a unit spends $100,000 or less, and sets a higher figure of $200,000 or less for construction contracts awarded by the Department of General Services or the Department of Transportation.

For public bodies other than the State, § 17-103(b) adds an option: the public body may require payment or performance security on a contract that exceeds $100,000 but does not exceed the small procurement amount, as long as the security does not exceed 50% of the contract amount.

Because the bond statute now points to another section instead of stating a number, older guides that list a flat $100,000 threshold for Maryland are out of date. The bid documents will state the security required on a specific contract, and that is the figure to rely on.

Bid Bonds in Maryland

A bid bond guarantees that a contractor will honor its bid and sign the contract if it is awarded the work. On State construction procurements, State Finance and Procurement § 13-207 requires bid security when the price is expected to exceed the small procurement amount. The security must be at least 5% of the bid or price proposal.

The statute accepts three forms of bid security: a bond provided by a surety company authorized to do business in Maryland, cash, or another form of security allowed by regulation. Under § 13-208, a procurement officer who requires bid security must reject a bid that is not accompanied by proper security, subject to narrow exceptions for an insubstantial shortfall.

Sections 13-207 and 13-208 govern State procurement. Counties and municipalities set bid security in their own procurement rules, so the percentage and the accepted forms on a local project come from the solicitation.

Bid bonds are free through Surety Specialist once your bonding line is established. The surety earns its premium when you win the job and the performance and payment bonds are issued.

Performance Bonds in Maryland

A performance bond guarantees that the project will be completed according to the contract. Under § 17-103, performance security on a covered Maryland public contract must be in an amount the public body considers adequate for its protection. The statute does not fix a percentage.

State contracts are more specific. COMAR 21.06.07.10 requires a performance bond equal to at least 100% of the contract price on State construction contracts above the applicable small procurement amount. Local public bodies commonly ask for 100% as well, but the amount on a county or municipal job is set by that public body.

Section 17-104 lists the acceptable forms of security: a bond executed by a surety company authorized to do business in Maryland, cash in an amount equivalent to a bond, or other security satisfactory to the public body. Performance security may also take the form of a mortgage or deed of trust on Maryland real property, limited to 75% of the contractor's equity in the property.

Payment Bonds in Maryland

A payment bond protects the subcontractors and suppliers on a public job, who cannot file a mechanic's lien against public property. Section 17-103 sets payment security at at least 50% of the total amount payable under the contract.

On State construction contracts, COMAR 21.06.07.10 raises that to at least 100% of the contract price. Before solicitation, the head of a procurement agency may reduce the payment bond to not less than 50% of the contract price on a written determination that doing so is in the State's best interest.

The Act protects "suppliers," which § 17-101 defines as anyone who supplies labor or materials. The definition includes a lessor of equipment, to the extent of the fair rental value of the equipment.

Subdivision Bonds in Maryland

Subdivision bonds (also called site improvement bonds) guarantee that a developer will finish the public improvements tied to an approved plat, such as roads, storm drainage, water and sewer lines, and sidewalks. These guarantees are not part of the Little Miller Act. They are posted with the county or municipality that approves the development, under that jurisdiction's own subdivision and development regulations.

The amount, the accepted forms of guarantee, and the release and maintenance terms differ from one Maryland jurisdiction to the next, so the starting point is the approving agency's requirements for your project. Subdivision bond premiums typically run 1% to 3% of the bond amount per year, depending on the developer's financial condition, credit and experience.

Maryland Contractor Licensing

Maryland requires a construction license to do construction business in the state (Business Regulation § 17-602). A firm that is incorporated or has its principal office in another state needs a nonresident construction license in addition to any other license required by law. Section 17-602 does not call for a surety bond as a condition of the construction license.

Trade licenses and residential home improvement work are regulated separately, and some local jurisdictions and permits carry their own bond requirements. Confirm the licensing that applies to your trade and location before you bid.

Notice & Claim Requirements in Maryland

Payment bond rights on Maryland public projects are set out in §§ 17-108 and 17-109.

  • Waiting period: A supplier may sue on the payment security if it has not been paid in full within 90 days after the day it last supplied labor or materials.
  • Notice (no direct contract with the prime): A supplier whose contract is with a subcontractor or sub-subcontractor must give written notice to the prime contractor within 90 days after the labor or materials were last supplied. The notice must state the amount claimed and the person the labor or materials were supplied to with substantial accuracy.
  • How notice is sent: By certified mail to the contractor's residence or a place where the contractor has an office or does business.
  • Suit deadline: An action on the payment bond must be filed within one year after the public body finally accepts the work performed under the contract.
  • Venue: The county where the contract was executed and performed, or where the contractor has its principal place of business.

Note the trigger for the one-year deadline. In Maryland it runs from the public body's final acceptance of the work, not from the claimant's own last day of work, which is how the federal Miller Act and many other states measure it.

Retainage on bonded public contracts

Where the contractor has furnished 100% payment security and 100% performance security, retainage may not exceed 5% of the total contract amount. The cap appears in § 13-225 for State construction contracts and in § 17-110 for public bodies generally. On State contracts, a contractor may not retain a larger percentage from a subcontractor than the State retains from the contractor. Section 17-110 also requires the public body to release retainage within 120 days after satisfactory completion of the contract.

Frequently Asked Questions About Maryland Contract Bonds

Under Maryland's Little Miller Act (State Finance and Procurement § 17-103), a contractor must provide payment security and performance security before a public body awards a construction contract that exceeds the small procurement amount set in § 13-109. That amount is $100,000 generally and $200,000 for construction procured by the Department of General Services or the Department of Transportation. The statute covers the State, counties, municipal corporations, other political subdivisions, public instrumentalities and any governmental unit authorized to award a contract.

The statute no longer states a fixed dollar figure. Section 17-103 points to the small procurement amount in § 13-109, which is $100,000 as a general rule and $200,000 for construction contracts awarded by the Department of General Services or the Department of Transportation. Older guides that cite a flat $100,000 threshold predate that change. A public body other than the State may also require security on a contract that exceeds $100,000 but does not exceed the small procurement amount, capped at 50% of the contract amount. Check the solicitation for the figure that applies to your contract.

The statute sets payment security at a minimum of 50% of the total amount payable under the contract and leaves performance security at an amount the public body considers adequate for its protection. State contracts go further by regulation: COMAR 21.06.07.10 requires a performance bond and a payment bond each equal to at least 100% of the contract price on State construction contracts above the applicable small procurement amount. Before solicitation, the head of a procurement agency may reduce the payment bond to not less than 50% with a written determination.

On State construction procurements, yes, once the price is expected to exceed the small procurement amount. State Finance and Procurement § 13-207 requires bid security of at least 5% of the bid or price proposal, in the form of a bond from a surety company authorized to do business in Maryland, cash, or another form allowed by regulation. Under § 13-208 a bid that is not accompanied by proper security must be rejected, with narrow exceptions. Counties and municipalities set bid security in their own procurement rules.

A supplier with a direct contract with the prime contractor does not have to give advance notice. A supplier whose contract is with a subcontractor or sub-subcontractor must give written notice to the prime contractor within 90 days after the labor or materials were last supplied. The notice must state the amount claimed and the person the labor or materials were supplied to with substantial accuracy, and it must be sent by certified mail to the contractor's residence or a place where the contractor has an office or does business (§ 17-108).

A supplier may sue if it has not been paid in full within 90 days after it last supplied labor or materials. The action must be filed within one year after the public body finally accepts the work performed under the contract (§ 17-109). That clock runs from the public body's final acceptance, not from the claimant's own last day on the job. Suit is filed in the county where the contract was executed and performed or where the contractor has its principal place of business.

Where the contractor has furnished 100% payment security and 100% performance security, retainage may not exceed 5% of the total contract amount. That cap appears in § 13-225 for State construction contracts and in § 17-110 for public bodies generally. Section 17-110 also requires the public body to release retainage within 120 days after satisfactory completion of the contract.

Performance and payment bond premiums typically run 1% to 3% of the contract price, depending on the contractor's credit, financial statements and experience. Bid bonds are free through Surety Specialist once your bonding line is established. Subdivision bonds typically cost 1% to 3% of the bond amount per year.

Request a Maryland Contract Bond Quote

Fill out the form below and one of our Maryland bond specialists will contact you within one business day with a personalized quote. There is no cost or obligation.

Please enter your full name.
Please enter your company name.
Please enter a valid email address.
Please enter a valid phone number.
Please select a bond type.
Please select a bond amount range.

Thank you! Your Maryland contract bond quote request has been submitted. One of our bond specialists will contact you within one business day.

Ready to Get Bonded in Maryland?

Contact our team today for a free, no-obligation Maryland contract bond quote. We serve contractors in all 23 Maryland counties and Baltimore City, with fast approvals from 80+ top-rated sureties.

Request a Quote Call 877-914-0909